In excavation work, what does surcharge near the trench edge mean?
Correct Answer
C) Extra load placed near the excavation, such as spoil, equipment, or stored pipe
A surcharge is an additional load near the excavation edge that can increase pressure on trench walls, such as spoil piles, equipment, or materials. Other choices use unrelated cost, water, or bedding terms.
Why This Is the Correct Answer
A surcharge is an additional load near the excavation edge that can increase pressure on trench walls, such as spoil piles, equipment, or materials. Other choices use unrelated cost, water, or bedding terms.
Why the Other Options Are Wrong
Option A: The fee for hauling excess soil
The trap in A is The fee for hauling excess soil. That selection is wrong because it points to The fee for hauling excess soil, but.
Option B: The water added for dust control
Choice B gives The water added for dust control. Its specific error: it answers the Surcharge prompt with the wrong practical move.
Option D: The pipe bedding below the haunch
In site construction, The pipe bedding below the haunch is the wrong selection for Surcharge: it solves the wrong trade problem; the field result tied to Surcharge is Extra load placed near the excavation, such as spoil, equipment, or stored pipe.
Memory Technique
Use surcharge as the label and Extra load placed near the excavation, such as spoil, equipment, or stored pipe as the definition to recall under pressure.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Excavation stability and surcharge loads" to confirm that A surcharge is an additional load near the excavation edge that can increase pressure on trench walls, such as spoil piles, equipment, or materials.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
