What is a liquidated damages clause intended to do?
Correct Answer
C) Set an agreed daily amount for delay damages when actual damages are difficult to determine.
Liquidated damages set a contract amount for delay, not a penalty or extra-work payment.
Why This Is the Correct Answer
Liquidated damages set a contract amount for delay, not a penalty or extra-work payment.
Why the Other Options Are Wrong
Option A: Resolve liquidated damages clause by choosing to punish bidders for asking RFIs
The trap in A is Punish bidders for asking RFIs. That selection is wrong because it shifts the question into contract administration money flow.
Option B: The contractor should replace all insurance as a substitute for the required liquidated damages clause process
Choice B gives Replace all insurance. Its specific error: it treats Liquidated damages clause as optional.
Option D: To pay for owner-directed extra scope while resolving liquidated damages clause
In procurement and contracting, Pay for owner-directed extra scope. is the wrong selection for Liquidated damages clause: it shifts the question into contract administration money flow.
Memory Technique
Make liquidated damages clause a tabbed card: cite the exact condition, then choose Set an agreed daily amount for delay damages when actual damages are difficult to determine.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Liquidated damages" to confirm that Liquidated damages set a contract amount for delay, not a penalty or extra-work payment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In the beam connection section, which labeled layer is immediately above BOLT GROUP?
Next Question
The instructions to bidders require bid security equal to 5 percent of the bid amount. A bidder submits a bond for a smaller fixed dollar amount. What controls the required bid security?
