A superintendent compares the field record with the contract: what is the purpose of an RFI when contract documents conflict?
Correct Answer
A) Request clarification before proceeding with affected work
Request clarification before proceeding with affected work is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 222.
Why This Is the Correct Answer
Request clarification before proceeding with affected work is the controlling requirement
Why the Other Options Are Wrong
Option B: Approve a substitution automatically; without contract authorization
In procurement and contracting, Approve a substitution automatically; without contract authorization is the wrong selection for RFI: the option delays or omits the controlling step.
Option C: Waive contract time
The trap in C is Waive contract time. That selection is wrong because it removes the controlling RFI requirement instead of meeting it.
Option D: Release retainage
Choice D gives Release retainage. Its specific error: it names a financial document or payment mechanism, not the RFI action/result stated by.
Memory Technique
File RFI under a warning sign: condition first, number or duty second, answer Request clarification before proceeding with affected work.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Requests for information" to confirm that Request clarification before proceeding with affected work is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass