A contraction joint is detailed in a slab-on-grade panel. Its primary function is to do what?
Correct Answer
A) Create a planned weakened plane where shrinkage cracking can occur in a controlled line
A contraction joint intentionally weakens a line so shrinkage cracking is controlled at that location. Other choices: it does not thicken the slab, eliminate shrinkage, or automatically serve as a doweled load-transfer construction joint.
Why This Is the Correct Answer
A contraction joint intentionally weakens a line so shrinkage cracking is controlled at that location.
Why the Other Options Are Wrong
Option B: The superintendent should increase slab thickness under rack posts
In concrete work, Increase slab thickness under rack posts is the wrong selection for Control joints: it leaves out the controlling Control joints result: Create a planned weakened plane where shrinkage cracking can occur in a controlled line.
Option C: Eliminate all drying shrinkage in the concrete, leaving control joints unverified
The trap in C is Eliminate all drying shrinkage in the concrete. That selection is wrong because it removes the controlling Control joints requirement instead of meeting it.
Option D: Transfer vertical load the same way a doweled construction joint does
Choice D gives Transfer vertical load the same way a doweled construction joint does. Its specific error: the option does not produce the required Control joints outcome, Create a planned weakened plane where shrinkage cracking can occur in a controlled line.
Memory Technique
Attach control joints to a scope box: remember the function, then the wording Create a planned weakened plane where shrinkage cracking can occur in a controlled line.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Slab contraction joints" to confirm that A contraction joint intentionally weakens a line so shrinkage cracking is controlled at that location.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass