NASCLAProcurement and Contracting Requirementsmedium

A supplier ships a cheaper pump that was never approved as equal. What should the contractor do?

Correct Answer

C) Hold the item and process the substitution or require the specified/approved product.

Unapproved substitutions are not contract-compliant merely because they arrive or cost less.

Answer Options
A
Install it because it is cheaper, leaving unapproved substitution delivery unverified
B
Close contract execution first and resolve the unapproved substitution delivery record later
C
Hold the item and process the substitution or require the specified/approved product.
D
Assume the contractor may pay final retainage when applying unapproved substitution delivery

Why This Is the Correct Answer

Unapproved substitutions are not contract-compliant merely because they arrive or cost less.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.