A product-data submittal is returned 'revise and resubmit.' What is the correct next control step?
Correct Answer
C) Revise the submittal and resubmit it through the required review channel.
Revise-and-resubmit status means the item is not ready for unrestricted use.
Why This Is the Correct Answer
Revise-and-resubmit status means the item is not ready for unrestricted use.
Why the Other Options Are Wrong
Option A: The project manager should install the product immediately
Choice A (Install the product immediately.) is rejected because it answers the Submittal resubmission control prompt with the wrong practical move.
Option B: The project manager should delete the submittal from the log
In general project requirements, Delete the submittal from the log. is the wrong selection for Submittal resubmission control: it removes the controlling Submittal resubmission control requirement instead of meeting it.
Option D: Treat the first review as final approval
Choice D gives Treat the first review as final approval. Its specific error: the option does not produce the required Submittal resubmission control outcome, Revise the submittal and resubmit it through the required review channel.
Memory Technique
Picture a flashing lip on the jobsite; submittal resubmission control is solved by the action that leads to Revise the submittal and resubmit it through the required review channel.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Revise-and-resubmit status means the item is not ready for unrestricted use.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass