A contract assesses $1,500 per calendar day of delay. If completion is 8 days late, what liquidated damages amount is assessed?

Correct Answer

A) $12,000

Liquidated damages are 8 x $1,500 = $12,000.

Answer Options
A
$12,000
B
$8,000
C
$10,500
D
$18,000

Why This Is the Correct Answer

Liquidated damages are 8 x $1,500 = $12,000.

Why the Other Options Are Wrong

Option B: $8,000

liquidated damages, choice a: $8,000 backs into 5.33 when divided by $1,500; the accepted setup gives 8 on that same base.

Option C: $10,500

liquidated damages, choice b: $10,500 backs into 7 when divided by $1,500; the accepted setup gives 8 on that same base.

Option D: $18,000

liquidated damages, choice d: $18,000 backs into 12 when divided by $1,500; the accepted setup gives 8 on that same base.

Memory Technique

Store liquidated damages with its last math move; nearby answers are usually unfinished versions of $12,000.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "liquidated damages" to confirm that Liquidated damages are 8 x $1,500 = $12,000.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.