A contract assesses $1,500 per calendar day of delay. If completion is 8 days late, what liquidated damages amount is assessed?
Correct Answer
A) $12,000
Liquidated damages are 8 x $1,500 = $12,000.
Why This Is the Correct Answer
Liquidated damages are 8 x $1,500 = $12,000.
Why the Other Options Are Wrong
Option B: $8,000
liquidated damages, choice a: $8,000 backs into 5.33 when divided by $1,500; the accepted setup gives 8 on that same base.
Option C: $10,500
liquidated damages, choice b: $10,500 backs into 7 when divided by $1,500; the accepted setup gives 8 on that same base.
Option D: $18,000
liquidated damages, choice d: $18,000 backs into 12 when divided by $1,500; the accepted setup gives 8 on that same base.
Memory Technique
Store liquidated damages with its last math move; nearby answers are usually unfinished versions of $12,000.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "liquidated damages" to confirm that Liquidated damages are 8 x $1,500 = $12,000.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
