EstatePass
NASCLAProcurement and Contracting Requirementsmedium

A $35,000 allowance is reconciled to an approved cost of $41,800. What contract increase is needed before markup terms?

Correct Answer

C) $6,800

Allowance overrun is $41,800 - $35,000 = $6,800.

Answer Options
A
$5,800
B
$35,000
C
$6,800
D
$76,800

Why This Is the Correct Answer

Allowance overrun is $41,800 - $35,000 = $6,800.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.