A $35,000 allowance is reconciled to an approved cost of $41,800. What contract increase is needed before markup terms?

Correct Answer

C) $6,800

Allowance overrun is $41,800 - $35,000 = $6,800.

Answer Options
A
$5,800
B
$35,000
C
$6,800
D
$76,800

Why This Is the Correct Answer

Allowance overrun is $41,800 - $35,000 = $6,800.

Why the Other Options Are Wrong

Option A: $5,800

allowance overrun, choice a: $5,800 is wrong because $5,800 takes one allowance-side amount as the adjustment.

Option B: $35,000

allowance overrun, choice c: $35,000 takes one allowance-side amount as the adjustment.

Option D: $76,800

allowance overrun, choice d: $76,800 is wrong because $76,800 takes one allowance-side amount as the adjustment.

Memory Technique

Say the allowance overrun rule aloud as a chain; the chain ends at $6,800, not an intermediate stop.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "allowance reconciliation" to confirm that Allowance overrun is $41,800 - $35,000 = $6,800.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.