A subcontractor requests payment for switchgear stored off site. What backup is normally needed?
Correct Answer
D) Invoices, proof of storage, insurance, ownership or allocation, and contract-required approvals.
Stored-material payment normally requires evidence that the material is purchased, protected, insured, and allocated to the project.
Why This Is the Correct Answer
Stored-material payment normally requires evidence that the material is purchased, protected, insured, and allocated to the project.
Why the Other Options Are Wrong
Option A: Base the stored material pay request response on a verbal statement
The trap in A is A verbal statement only. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Stored material pay request.
Option B: The contractor should approve the stored-material payment from a pay-application line item alone
Choice B gives A bid protest letter. Its specific error: it shifts the question into contract administration money flow.
Option C: The contractor should use a draft submittal log without invoice, insurance, or storage backup
Choice C (A blank RFI form) is rejected because it points to A blank RFI form, but.
Memory Technique
Use the phrase "problem, control, result" for stored material pay request; the result side is Invoices, proof of storage, insurance, ownership or allocation, and contract-required approvals.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored-material payment" to confirm that Stored-material payment normally requires evidence that the material is purchased, protected, insured, and allocated to the project.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass