The weekly OAC agenda includes this unresolved item: why is a front-loaded schedule of values a payment concern?
Correct Answer
D) It can shift payment ahead of actual earned value
It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 444. Other choices: the distractors describe unrelated administration, payment, or closeout ideas.
Why This Is the Correct Answer
It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 444.
Why the Other Options Are Wrong
Option A: Use front loading to improve record drawings
Choice A gives It improves record drawings. Its specific error: the option does not produce the required Front loading outcome.
Option B: Use front loading to delete retainage
Choice B (It deletes retainage) is rejected because it treats Front loading as optional.
Option C: Use front loading to replace insurance
In procurement and contracting, It replaces insurance is the wrong selection for Front loading: the option tries to substitute, waive, or delete the Front loading control; the item instead requires.
Memory Technique
Keep front loading as a cause-to-effect card with It can shift payment ahead of actual earned value on the back.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "SOV front loading" to confirm that It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 444.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A drywall foreman checks screw spacing along the supported edge of a gypsum wall panel. Which maximum spacing is commonly used at supported wall edges?
Next Question
Twelve square concrete columns are each 18 in. by 18 in. and 12 ft tall. Ignoring waste, how much concrete is required?