Twelve square concrete columns are each 18 in. by 18 in. and 12 ft tall. Ignoring waste, how much concrete is required?
Correct Answer
D) 12.0 cy
One column contains 1.5 x 1.5 x 12 = 27 cf. Twelve columns contain 324 cf, and 324/27 = 12.0 cy. Other choices: 9.0 cy uses a 15 in. side, 10.5 cy rounds down incorrectly, and 13.5 cy adds waste not requested.
Why This Is the Correct Answer
One column contains 1.5 x 1.5 x 12 = 27 cf. Twelve columns contain 324 cf, and 324/27 = 12.0 cy.
Why the Other Options Are Wrong
Option A: 9.0 cy
column volume, choice a: 9.0 cy is wrong because 9.0 cy equals about 243 cf after cubic-yard conversion; the accepted cubic-foot volume is 27 cf before dividing by 27 in.
Option B: 10.5 cy
column volume, choice b: 10.5 cy equals about 283.5 cf after cubic-yard conversion; the accepted cubic-foot volume is 27 cf before dividing by 27 in.
Option C: 13.5 cy
column volume, choice c: 13.5 cy equals about 364.5 cf after cubic-yard conversion; the accepted cubic-foot volume is 27 cf before dividing by 27 in.
Memory Technique
Picture a dimension string labeled column volume: finish every operation before accepting 12.0 cy.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Concrete quantity takeoff - columns" to confirm that One column contains 1.5 x 1.5 x 12 = 27 cf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study