In a contract estimate, an allowance is used when:
Correct Answer
C) A defined amount is carried for work or products not fully selected at bid time
An allowance carries a stated amount for a defined item whose exact selection or cost is not fully known at bid time. Other choices are inconsistent with why allowances are used.
Why This Is the Correct Answer
An allowance carries a stated amount for a defined item whose exact selection or cost is not fully known at bid time. Other choices are inconsistent with why allowances are used.
Why the Other Options Are Wrong
Option A: Every product has already been fully selected and priced
The trap in A is Every product has already been fully selected and priced. That selection is wrong because it leaves out the controlling Allowance result: A defined amount is carried for work or products not fully selected at bid time.
Option B: The contractor wants to remove work from the contract, leaving allowance unverified
Choice B gives The contractor wants to remove work from the contract. Its specific error: the choice would not get the project to A defined amount is carried for work or products not fully selected at bid time, which is the Allowance result verified by the source.
Option D: The owner has waived all change orders, leaving allowance unverified
In procurement and contracting, The owner has waived all change orders is the wrong selection for Allowance: it treats Allowance as optional.
Memory Technique
Make allowance a purpose cue; if the choice changes the purpose, it cannot be A defined amount is carried for work or products not fully selected at bid time.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Allowances" to confirm that An allowance carries a stated amount for a defined item whose exact selection or cost is not fully known at bid time.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
