The contract sets liquidated damages at $1,500 per calendar day. If substantial completion is 7 days late, what amount is assessed?

Correct Answer

B) $10,500

Liquidated damages are 7 days x $1,500/day = $10,500. Other choices use five, six, or eight days rather than the stated seven-day delay.

Answer Options
A
$7,500
B
$10,500
C
$9,000
D
$12,000

Why This Is the Correct Answer

Liquidated damages are 7 days x $1,500/day = $10,500. Other choices use five, six, or eight days rather than the stated seven-day delay.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.