Owner-furnished kitchen equipment arrives three weeks late and blocks rough-in completion. What should the contractor do under normal contract administration?
Correct Answer
C) Submit required notice and schedule support for any time or cost impact caused by the late owner-furnished equipment
Late owner-furnished equipment may support a time or cost claim only if the contractor follows notice and support requirements. Other choices waive, remove, or falsify the issue.
Why This Is the Correct Answer
Late owner-furnished equipment may support a time or cost claim only if the contractor follows notice and support requirements. Other choices waive, remove, or falsify the issue.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
On a fast-track school project, a cheaper product differs from the specified basis and has not been approved. What should happen before purchase?
Next Question
A contract clause is applied to this fact pattern: which review asks whether the bidder has capacity, experience, resources, and integrity to perform?
