Owner-furnished kitchen equipment arrives three weeks late and blocks rough-in completion. What should the contractor do under normal contract administration?
Correct Answer
C) Submit required notice and schedule support for any time or cost impact caused by the late owner-furnished equipment
Late owner-furnished equipment may support a time or cost claim only if the contractor follows notice and support requirements. Other choices waive, remove, or falsify the issue.
Why This Is the Correct Answer
Late owner-furnished equipment may support a time or cost claim only if the contractor follows notice and support requirements. Other choices waive, remove, or falsify the issue.
Why the Other Options Are Wrong
Option A: Backdate the delivery ticket
Choice A (Backdate the delivery ticket) is rejected because it leaves out the controlling Owner-furnished equipment delay result: Submit required notice and schedule support for any time or cost impact caused by the late.
Option B: Absorb every impact without notice
In procurement and contracting, Absorb every impact without notice is the wrong selection for Owner-furnished equipment delay: the option delays or omits the controlling step.
Option D: The contractor should delete the kitchen equipment from the project
Choice D gives Delete the kitchen equipment from the project. Its specific error: it removes the controlling Owner-furnished equipment delay requirement instead of meeting it.
Memory Technique
Remember owner-furnished equipment delay by its jobsite consequence: the correct move points to Submit required notice and schedule support for any time or cost impact caused by the late owner-furnished equipment.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - liquidated damages / delay / claim notice to confirm that Late owner-furnished equipment may support a time or cost claim only if the contractor follows notice and support requirements.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
On a fast-track school project, a cheaper product differs from the specified basis and has not been approved. What should happen before purchase?
Next Question
A contract clause is applied to this fact pattern: which review asks whether the bidder has capacity, experience, resources, and integrity to perform?
