The practical difference between an allowance and a contingency is that:
Correct Answer
B) An allowance carries money for a defined item not fully selected, while contingency covers defined risk under contract rules
An allowance is a stated amount for a defined item not fully selected or priced; contingency is a reserve for risks or costs allowed by the contract. Other choices merge or misstate the terms.
Why This Is the Correct Answer
An allowance is a stated amount for a defined item not fully selected or priced; contingency is a reserve for risks or costs allowed by the contract. Other choices merge or misstate the terms.
Why the Other Options Are Wrong
Option A: Use allowance versus contingency to are always identical contract terms
Choice A (They are always identical contract terms) is rejected because it points to They are always identical contract terms, but.
Option C: Classify the condition as an allowance is a bid bond
The trap in C is An allowance is a bid bond. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Option D: Classify the condition as a contingency is always paid to the low bidder before work starts
Choice D gives A contingency is always paid to the low bidder before work starts. Its specific error: it shifts the question into contract administration money flow.
Memory Technique
Make allowance versus contingency a purpose cue; if the choice changes the purpose, it cannot be An allowance carries money for a defined item not fully selected, while contingency covers defined risk under contract rules.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Allowance and contingency concepts" to confirm that An allowance is a stated amount for a defined item not fully selected or priced; contingency is a reserve for risks or costs allowed by the contract.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
