A deck sheet is about to be laid with one end barely catching the beam flange because the panel was miscut. What should the deck crew do?
Correct Answer
C) Ensure full support by structural members during placement or replace the panel
OSHA 1926.754(e)(5)(ii) requires metal decking panels during initial placement to be placed to ensure full support by structural members. Other choices rely on unstable support or delay securement.
Why This Is the Correct Answer
OSHA 1926.754(e)(5)(ii) requires metal decking panels during initial placement to be placed to ensure full support by structural members. Other choices rely on unstable support or delay securement.
Why the Other Options Are Wrong
Option A: Place the panel and rely on side laps, leaving deck panel support unverified
Choice A (Place the panel and rely on side laps) is rejected because it answers the Deck panel support prompt with the wrong practical move.
Option B: Stand on the unsupported end to hold it down, leaving deck panel support unverified
In metals work, Stand on the unsupported end to hold it down is the wrong selection for Deck panel support: it leaves out the controlling Deck panel support result: E.
Option D: The crew should attach it only after concrete is poured
Choice D gives Attach it only after concrete is poured. Its specific error: the action skips the timing, documentation, or field-control step needed for Deck panel support.
Memory Technique
Pair deck panel support with the real field trigger, then choose the response that produces Ensure full support by structural members during placement or replace the panel.
Reference Hint
Open SDI Manual of Construction with Steel Deck, 2016; 29 CFR 1926 Subpart R; use 29 CFR 1926.754(e)(5)(ii) to confirm that OSHA 1926.754(e)(5)(ii) requires metal decking panels during initial placement to be placed to ensure full support by structural members.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass