How much outward or downward force must a construction guardrail top rail generally withstand?
Correct Answer
B) At least 200 lb
OSHA fall-protection criteria require top rails to withstand at least 200 lb applied outward or downward.
Why This Is the Correct Answer
OSHA fall-protection criteria require top rails to withstand at least 200 lb applied outward or downward.
Why the Other Options Are Wrong
Option A: At least 50 lb
Choice A (At least 50 lb) is rejected because At least 50 lb is the wrong OSHA fall-protection number for the item asked.
Option C: At least 100 lb
The trap in C is At least 100 lb. That selection is wrong because At least 100 lb is the wrong OSHA fall-protection number for the item asked.
Option D: Only the weight of the rail
Choice D gives Only the weight of the rail. Its specific error: it leaves the work at an informal or incomplete stage, while Guardrail top rail force - much outward downward force construction requires At least 200 lb. The accepted answer is At least 200 lb.
Memory Technique
Make guardrail top rail force - much outward downward force construction a tabbed card: cite the exact condition, then choose At least 200 lb.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use 29 CFR 1926 Subpart M - Β§1926.502(b) to confirm that OSHA fall-protection criteria require top rails to withstand at least 200 lb applied outward or downward.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
