EstatePass
NASCLAGeneral Reqmedium22% of exam part

Anchor embeds are found out of tolerance before concrete placement. What is the best quality response?

Correct Answer

C) Stop affected placement, document the issue, and obtain approved correction before proceeding.

Out-of-tolerance embeds should be corrected before concrete locks in the defect.

Answer Options
A
The project manager should pour concrete to keep the schedule
B
The project manager should cut the embeds off after cure
C
Stop affected placement, document the issue, and obtain approved correction before proceeding.
D
Ignore because embeds are concealed

Why This Is the Correct Answer

Out-of-tolerance embeds should be corrected before concrete locks in the defect.

Why the Other Options Are Wrong

Option A: The project manager should pour concrete to keep the schedule

The trap in A is Pour concrete to keep the schedule. That selection is wrong because the option shifts to a different trade task; the tested Nonconforming embed function or field correction is Stop affected placement, document the issue, and obtain approved correction before proceeding.; Quality problems found before placement are corrected before proceeding.

Option B: The project manager should cut the embeds off after cure

Choice B gives Cut the embeds off after cure. Its specific error: the choice would not get the project to Stop affected placement, document the issue, and obtain approved correction before proceeding.

Option D: Ignore because embeds are concealed

In general project requirements, Ignore because embeds are concealed. is the wrong selection for Nonconforming embed: it leaves the work at an informal or incomplete stage, while Nonconforming embed requires Stop affected placement, document the issue, and obtain approved correction before proceeding.

Memory Technique

Remember nonconforming embed by its jobsite consequence: the correct move points to Stop affected placement, document the issue, and obtain approved correction before proceeding.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - quality control / nonconformance / corrective action to confirm that Out-of-tolerance embeds should be corrected before concrete locks in the defect.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.