Anchor embeds are found out of tolerance before concrete placement. What is the best quality response?
Correct Answer
C) Stop affected placement, document the issue, and obtain approved correction before proceeding.
Out-of-tolerance embeds should be corrected before concrete locks in the defect.
Why This Is the Correct Answer
Out-of-tolerance embeds should be corrected before concrete locks in the defect.
Why the Other Options Are Wrong
Option A: The project manager should pour concrete to keep the schedule
The trap in A is Pour concrete to keep the schedule. That selection is wrong because the option shifts to a different trade task; the tested Nonconforming embed function or field correction is Stop affected placement, document the issue, and obtain approved correction before proceeding.; Quality problems found before placement are corrected before proceeding.
Option B: The project manager should cut the embeds off after cure
Choice B gives Cut the embeds off after cure. Its specific error: the choice would not get the project to Stop affected placement, document the issue, and obtain approved correction before proceeding.
Option D: Ignore because embeds are concealed
In general project requirements, Ignore because embeds are concealed. is the wrong selection for Nonconforming embed: it leaves the work at an informal or incomplete stage, while Nonconforming embed requires Stop affected placement, document the issue, and obtain approved correction before proceeding.
Memory Technique
Remember nonconforming embed by its jobsite consequence: the correct move points to Stop affected placement, document the issue, and obtain approved correction before proceeding.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - quality control / nonconformance / corrective action to confirm that Out-of-tolerance embeds should be corrected before concrete locks in the defect.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?