A fatal fall occurs on a construction site. Within what time must the employer report the fatality to OSHA?
Correct Answer
A) Within 8 hours
OSHA requires work-related fatalities to be reported within 8 hours. The other periods apply to other records or severe-injury reporting.
Why This Is the Correct Answer
OSHA requires work-related fatalities to be reported within 8 hours. The other periods apply to other records or severe-injury reporting.
Why the Other Options Are Wrong
Option B: Within 24 hours
Choice B (Within 24 hours) is rejected because Within 24 hours is a different published number than the cited OSHA fatality reporting value; OSHA severe injury reporting supports Within 8 hours. The cited answer is Within 8 hours.
Option C: Within 3 business days
In general project requirements, Within 3 business days is the wrong selection for OSHA fatality reporting: Within 3 business days is a different published number than the cited OSHA fatality reporting value; OSHA severe injury reporting supports Within 8 hours.
Option D: With the annual OSHA 300A posting
The trap in D is With the annual OSHA 300A posting. That selection is wrong because With the annual OSHA 300A posting is a different published number than the cited OSHA fatality reporting value; OSHA severe injury reporting supports Within 8 hours; A work-related fatality must be reported to OSHA within 8 hours.
Memory Technique
File OSHA fatality reporting under a dimension string: condition first, number or duty second, answer Within 8 hours.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use OSHA reporting / recordkeeping topic to confirm that OSHA requires work-related fatalities to be reported within 8 hours.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?