A claims log entry raises this question: what extinguisher coverage applies in protected building areas?
Correct Answer
A) At least one 2A extinguisher per 3,000 sf or major fraction, within 100 ft travel
At least one 2A extinguisher per 3,000 sf or major fraction, within 100 ft travel is the controlling requirement.150(c)(1)(i). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 136.
Why This Is the Correct Answer
At least one 2A extinguisher per 3,000 sf or major fraction, within 100 ft travel is the controlling requirement.150(c)(1)(i).
Why the Other Options Are Wrong
Option B: Limit fire extinguishers to one extinguisher per trailer only
Choice B gives One extinguisher per trailer only. Its specific error: the action skips the timing, documentation, or field-control step needed for Fire extinguishers.
Option C: Apply the One 1A per 10,000 sf limit to the fire extinguishers check, leaving fire extinguishers unverified
Choice C (One 1A per 10,000 sf) is rejected because One 1A per 10,000 sf is a different published number than the cited Fire extinguishers value; 29 CFR 1926.150(c)(1)(i) supports.
Option D: Apply none until sprinklers are active to the fire extinguishers condition
In general project requirements, None until sprinklers are active is the wrong selection for Fire extinguishers: it leaves out the controlling Fire extinguishers result.
Memory Technique
Treat fire extinguishers like a labeled shelf; only the matching condition belongs with At least one 2A extinguisher per 3,000 sf or major fraction, within 100 ft travel.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.150(c)(1)(i) to confirm that At least one 2A extinguisher per 3,000 sf or major fraction, within 100 ft travel is the controlling requirement.150(c)(1)(i).
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass