A crew plans to add temporary heaters and lights to a floor already near panel capacity. What should be checked first?
Correct Answer
C) Temporary power capacity, circuit protection, cords, GFCI requirements, and fire risk.
Temporary power loads must be coordinated for capacity, protection, and safety before use.
Why This Is the Correct Answer
Temporary power loads must be coordinated for capacity, protection, and safety before use.
Why the Other Options Are Wrong
Option A: Limit temporary power coordination to the color of extension cords
In general project requirements, Only the color of extension cords. is the wrong selection for Temporary power coordination: the option delays or omits the controlling step.
Option B: Base the temporary power coordination response on the pay application line item
The trap in B is Only the pay application line item. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Temporary power coordination.
Option D: Base the temporary power coordination response on the final O&M manual only
Choice D (Only the final O&M manual.) is rejected because it leaves the work at an informal or incomplete stage, while Temporary power coordination requires Temporary power capacity, circuit protection, cords, GFCI requirements, and fire risk.
Memory Technique
Picture a checkpoint on the jobsite; temporary power coordination is solved by the action that leads to Temporary power capacity, circuit protection, cords, GFCI requirements, and fire risk.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - meetings / coordination / action items to confirm that Temporary power loads must be coordinated for capacity, protection, and safety before use.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass