A protected building area is being laid out during construction. What portable fire extinguisher coverage is required by the OSHA construction fire-protection rule?
Correct Answer
B) At least one 2A extinguisher per 3,000 sf or major fraction, with travel distance not over 100 ft
OSHA requires a fire extinguisher rated not less than 2A for each 3,000 sf or major fraction of protected building area, with travel distance not over 100 ft. Other choices understate the rating, restrict coverage to the trailer, or wait too long.
Why This Is the Correct Answer
OSHA requires a fire extinguisher rated not less than 2A for each 3,000 sf or major fraction of protected building area, with travel distance not over 100 ft. Other choices understate the rating, restrict coverage to the trailer, or wait too long.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The bid captain reviews the final hour checklist: wall cavities are ready for drywall before the required inspection occurs. What should the superintendent do?
Next Question
Under OSHA construction fire-protection rules, what is the maximum travel distance generally allowed to a 2A-rated fire extinguisher provided for ordinary combustible materials?
