A protected building area is being laid out during construction. What portable fire extinguisher coverage is required by the OSHA construction fire-protection rule?
Correct Answer
B) At least one 2A extinguisher per 3,000 sf or major fraction, with travel distance not over 100 ft
OSHA requires a fire extinguisher rated not less than 2A for each 3,000 sf or major fraction of protected building area, with travel distance not over 100 ft. Other choices understate the rating, restrict coverage to the trailer, or wait too long.
Why This Is the Correct Answer
OSHA requires a fire extinguisher rated not less than 2A for each 3,000 sf or major fraction of protected building area, with travel distance not over 100 ft. Other choices understate the rating, restrict coverage to the trailer, or wait too long.
Why the Other Options Are Wrong
Option A: Set the fire extinguisher coverage threshold at One 1A extinguisher per 1,000 sf with 50 ft travel distance
The trap in A is One 1A extinguisher per 1,000 sf with 50 ft travel distance. That selection is wrong because One 1A extinguisher per 1,000 sf with 50 ft travel distance is a different published number than the cited Fire extinguisher coverage value; 29 CFR 1926.150(c)(1)(i) supports At least one 2A extinguisher per 3,000 sf or major fraction, with travel distance not over 100 ft; At least one 2A extinguisher is required for each 3,000 sf or major fraction, and travel distance cannot exceed 100 ft.
Option C: One extinguisher only at the jobsite trailer
Choice C (One extinguisher only at the jobsite trailer) is rejected because the action skips the timing, documentation, or field-control step needed for Fire extinguisher coverage.
Option D: Treat the condition as requiring no extinguishers are needed until permanent fire sprinklers are active
In general project requirements, No extinguishers are needed until permanent fire sprinklers are active is the wrong selection for Fire extinguisher coverage: the choice would not get the project to At least one 2A extinguisher per 3,000 sf or major fraction, with travel distance not over 100 ft, which is the Fire extinguisher coverage result verified by the source.
Memory Technique
File fire extinguisher coverage under a scope box: condition first, number or duty second, answer At least one 2A extinguisher per 3,000 sf or major fraction, with travel distance not over 100 ft.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.150(c)(1)(i) to confirm that OSHA requires a fire extinguisher rated not less than 2A for each 3,000 sf or major fraction of protected building area, with travel distance not over 100 ft.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The bid captain reviews the final hour checklist: wall cavities are ready for drywall before the required inspection occurs. What should the superintendent do?
Next Question
Under OSHA construction fire-protection rules, what is the maximum travel distance generally allowed to a 2A-rated fire extinguisher provided for ordinary combustible materials?
