A tension lap splice is classified as Class B on the approved reinforcing schedule. How is the required lap length taken from ACI relative to the tension development length ld?
Correct Answer
C) 1.3 ld
ACI 318 tension lap-splice provisions use 1.3 ld for a Class B tension lap splice. Other choices: 0.75 ld is not a tension lap splice class, 1.0 ld describes the shorter Class A basis, and 2.0 ld is an overstatement for this classification.
Why This Is the Correct Answer
ACI 318 tension lap-splice provisions use 1.3 ld for a Class B tension lap splice.
Why the Other Options Are Wrong
Option A: 0.75 ld
The trap in A is 0.75 ld. That selection is wrong because 0.75 ld is a different published number than the cited Lap splices value; ACI 318-19 25.5 tension lap splices supports 1.3 ld; Class B tension lap splice length is 1.3 ld.
Option B: 1.0 ld
Choice B gives 1.0 ld. Its specific error: 1.0 ld is a different published number than the cited Lap splices value; ACI 318-19 25.5 tension lap splices supports 1.3 ld. The accepted answer is 1.3 ld.
Option D: 2.0 ld
In concrete work, 2.0 ld is the wrong selection for Lap splices: 2.0 ld is a different published number than the cited Lap splices value; ACI 318-19 25.5 tension lap splices supports 1.3 ld.
Memory Technique
File lap splices under a warning sign: condition first, number or duty second, answer 1.3 ld.
Reference Hint
Open ACI 318-19, Building Code Requirements for Structural Concrete; use ACI 318-19 25.5 tension lap splices to confirm that ACI 318 tension lap-splice provisions use 1.3 ld for a Class B tension lap splice.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?