The Eustis project has this cutting/welding condition: welding continues after fire watch leaves. Which fire-prevention control should be documented?
Correct Answer
B) maintain fire watch
Hot work requires controlling combustibles and maintaining fire-watch/fire-prevention measures as conditions require.
Why This Is the Correct Answer
Hot work requires controlling combustibles and maintaining fire-watch/fire-prevention measures as conditions require.
Why the Other Options Are Wrong
Option A: stop only if smoke shows
stop only if smoke shows may relate to another site control, but it does not remove or guard the hot-work fire prevention exposure being tested.
Option C: finish quickly with no watch
finish quickly with no watch may relate to another site control, but it does not remove or guard the hot-work fire prevention exposure being tested.
Option D: a passerby keeps an eye out
a passerby keeps an eye out may relate to another site control, but it does not remove or guard the hot-work fire prevention exposure being tested.
Memory Technique
If Superintendent Controls can still reach the worker, the control is decoration.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart J, 1926.352 Fire prevention and welding/cutting; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?