The Tampa crane pick has this communication condition: multiple spotters are giving conflicting directions. Which safety control should be used?
Correct Answer
D) stop lift and clarify signals
Crane operations need clear, qualified signaling when the operator's view or communication is limited.
Why This Is the Correct Answer
Crane operations need clear, qualified signaling when the operator's view or communication is limited.
Why the Other Options Are Wrong
Option A: follow the loudest spotter
follow the loudest spotter may relate to another site control, but it does not remove or guard the crane signal control exposure being tested.
Option B: average the conflicting signals
average the conflicting signals may relate to another site control, but it does not remove or guard the crane signal control exposure being tested.
Option C: speed up to clear confusion
speed up to clear confusion may relate to another site control, but it does not remove or guard the crane signal control exposure being tested.
Memory Technique
Crane Signal lock for Director Plans: operations is the harm, need is the guard.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart CC, 1926.1419 Signals and 1926.1428 Signal person qualifications; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The Orlando project has this confined-space condition: crew will enter a manhole with limited entry. Which safety control should be completed before entry?
Next Question
The construction team is coordinating a method decision because stud cavities will be concealed by gypsum board. Which coordination item is best?