A construction stairway has six risers and an unprotected open side. Which correction meets the stairrail requirement?
Correct Answer
A) Provide a compliant stairrail system along the open side and the required handrail.
A stairway with four or more risers, or rising more than 30 inches, whichever is less, requires at least one handrail and a stairrail system along each unprotected side or edge. Tape or a toeboard alone does not provide the required system. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.1052
Why This Is the Correct Answer
A stairway with four or more risers, or rising more than 30 inches, whichever is less, requires at least one handrail and a stairrail system along each unprotected side or edge. Tape or a toeboard alone does not provide the required system. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.1052
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Project Mgmt Questions
A sloped roof surface measures 7,360 square feet. Add 8% waste and express the result in 100-square-foot roofing squares, to the nearest 0.1 square.
Grinding metal creates flying-particle hazards to a worker’s eyes and face. Which PPE action addresses those hazards?
The project inspection plan requires in-wall rough-in approval before gypsum board conceals stud cavities. Which coordination item must be completed before close-in?
A low-slope roof detail requires base flashing continuous with the field membrane before its upper edge is counterflashed. The membrane-to-wall transition is not yet installed. Which listed step addresses that missing interface?
A membrane takeoff covers 13,720 square feet before 8% waste. Express the adjusted area in 100-square-foot roofing squares, to the nearest 0.1 square.
An office needs carpet tile over 9,975 square feet, plus one combined 15% allowance for waste and spare stock. Each carton supplies 48 square feet. How many whole cartons are needed?
A grout takeoff requires 11.5 cubic feet including its allowance. For this exercise, each bag yields 0.45 cubic foot. How many whole bags are needed?
A steel connection schedule identifies which joints require snug-tight installation and which require pretensioning. Which approach follows that schedule?
A sling’s required safe-working-load identification is illegible before a planned lift. Which action is required?
A supplied metal-deck takeoff calls for 18 approved pins per sheet over 175 sheets. Boxes contain 900 pins. With no additional allowance, how many whole boxes are required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
A contract requires written approval from its designated reviewer for any material substitution before purchase. Which listed process meets that requirement?
Next Question
A project sediment-control plan calls for perimeter silt fence at marked sheet-flow locations and protection at designated storm inlets. Which option implements those controls?