A planned permit-space entry is subject to 1926.1204, with no alternate-procedure exception. Required rescue arrangements are missing. What must be completed before entry?
Correct Answer
B) Establish the required rescue and emergency-response procedures.
The permit-space program must include procedures for summoning rescue and emergency services, rescuing entrants, and preventing unauthorized rescue attempts. Establish these arrangements before authorizing the stated entry. A brief task does not remove the duty, and an improvised attendant entry is not a rescue procedure. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.1204
Why This Is the Correct Answer
The permit-space program must include procedures for summoning rescue and emergency services, rescuing entrants, and preventing unauthorized rescue attempts. Establish these arrangements before authorizing the stated entry. A brief task does not remove the duty, and an improvised attendant entry is not a rescue procedure. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.1204
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Project Mgmt Questions
A sloped roof surface measures 7,360 square feet. Add 8% waste and express the result in 100-square-foot roofing squares, to the nearest 0.1 square.
Grinding metal creates flying-particle hazards to a worker’s eyes and face. Which PPE action addresses those hazards?
The project inspection plan requires in-wall rough-in approval before gypsum board conceals stud cavities. Which coordination item must be completed before close-in?
A low-slope roof detail requires base flashing continuous with the field membrane before its upper edge is counterflashed. The membrane-to-wall transition is not yet installed. Which listed step addresses that missing interface?
A membrane takeoff covers 13,720 square feet before 8% waste. Express the adjusted area in 100-square-foot roofing squares, to the nearest 0.1 square.
An office needs carpet tile over 9,975 square feet, plus one combined 15% allowance for waste and spare stock. Each carton supplies 48 square feet. How many whole cartons are needed?
A grout takeoff requires 11.5 cubic feet including its allowance. For this exercise, each bag yields 0.45 cubic foot. How many whole bags are needed?
A steel connection schedule identifies which joints require snug-tight installation and which require pretensioning. Which approach follows that schedule?
A sling’s required safe-working-load identification is illegible before a planned lift. Which action is required?
A supplied metal-deck takeoff calls for 18 approved pins per sheet over 175 sheets. Boxes contain 900 pins. With no additional allowance, how many whole boxes are required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
Selective demolition may affect load-bearing elements and utility services. Which listed action belongs before removal starts?
Next Question
Approved fabrication instructions require cutting and bending reinforcing bars on site. Which listed equipment can perform both operations, when rated for the bar size and grade?