Project MgmtConstructionmedium63% of exam part

While preparing the crew-release check for the university bookstore shell, the concrete washout solids produces 147 CY of solid waste volume, with 15% swell or handling allowance. Each container holds 10 CY. How many containers are required?

Correct Answer

A) 17 containers

Container count equals adjusted debris volume divided by container capacity, rounded up.

Answer Options
A
17 containers
B
15 containers
C
18 containers
D
16 containers

Why This Is the Correct Answer

Container count equals adjusted debris volume divided by container capacity, rounded up.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.