From the service yard slab plan, what slab area should be used for takeoff?
Correct Answer
B) 756 sf
The plan dimensions show 42 ft by 18 ft, so the takeoff area is 756 sf.
Why This Is the Correct Answer
The plan dimensions show 42 ft by 18 ft, so the takeoff area is 756 sf.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the pre-installation review, the field issue is that the project condition shows that frame must remain stable during erection. Which steel erection control is the best match?
Next Question
While preparing the crew-release check for the university bookstore shell, the concrete washout solids produces 147 CY of solid waste volume, with 15% swell or handling allowance. Each container holds 10 CY. How many containers are required?