While preparing the preconstruction estimate lock for the transit-platform kiosk, the floor area for carpet tile field is 14715 SF and the order includes 0% waste. How many square yards are required?
Correct Answer
A) 1,635.0 SY
Square yards equal square feet with waste divided by 9.
Why This Is the Correct Answer
Square yards equal square feet with waste divided by 9.
Why the Other Options Are Wrong
Option B: 14,715.0 SY
14,715.0 SY is above the supported result for carpet tile field; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option C: 1,471.5 SY
1,471.5 SY is below the supported result for carpet tile field; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 1,635.7 SY
1,635.7 SY is above the supported result for carpet tile field; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Estimator Converts takeoff: count the condition before counting the package.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Flooring; square-foot to square-yard conversion; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The field condition is: the project condition shows that fresh concrete must flow around congested reinforcement. Which consolidation method best matches the condition?
Next Question
On this project, the controlling condition is the project condition shows that the specification requires a mockup. Which quality-control step should be selected?