During the field-takeoff reconciliation at the stormwater-lift-station yard, the finished floor area for temporary floor protection is 9000 SF. With 12% waste and 40 SF per sheet or panel, how many sheets are required?
Correct Answer
B) 252 sheets
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why This Is the Correct Answer
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why the Other Options Are Wrong
Option A: 225 sheets
225 sheets is below the supported result for temporary floor protection; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 126 sheets
126 sheets is below the supported result for temporary floor protection; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 256 sheets
256 sheets is above the supported result for temporary floor protection; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to sheet, adjust for count, then let Carpenter Checks set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Temporary protection; sheet coverage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the look-ahead planning meeting at the visitor-center exhibit wall, the stair return run requires 443 LF of handrail tube stock plus 4% waste. Stock comes in 20 ft lengths. How many lengths are required?
Next Question
While preparing the field-takeoff reconciliation for the parking-garage stair tower, the aggregate delivery includes 147 tons of No. 57 stone. Each delivery truck carries 22 tons. How many truckloads are required?