During the subcontractor quantity check at the shipping-office break area, 106 sleeves are included in the firestopping sleeve work. At 1.0 labor hours per sleeve, how many labor hours are budgeted?
Correct Answer
A) 106.0 labor hours
Labor hours equal the number of units times the labor-hour factor per unit.
Why This Is the Correct Answer
Labor hours equal the number of units times the labor-hour factor per unit.
Why the Other Options Are Wrong
Option B: 148.4 labor hours
148.4 labor hours is above the supported result for firestopping sleeve work; it likely pays the wrong premium tier or counts the same hours twice.
Option C: 90.1 labor hours
90.1 labor hours is below the supported result for firestopping sleeve work; it likely skips a premium-pay or employer-cost component.
Option D: 106.7 labor hours
106.7 labor hours is above the supported result for firestopping sleeve work; it likely pays the wrong premium tier or counts the same hours twice.
Memory Technique
Firestopping ladder for Manager Checks: hours climb before dollars add up.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Firestopping methods; penetration labor; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The Palm Bay work area has this housekeeping condition: debris blocks the emergency route. Which safety correction should be made?
Next Question
At the clinic oxygen-storage pad, during the buyout verification pass, a sloped landing slab is 36 ft by 30 ft by 8 in. Including 7% waste, how many cubic yards of concrete are needed?