At the clinic oxygen-storage pad, during the buyout verification pass, a sloped landing slab is 36 ft by 30 ft by 8 in. Including 7% waste, how many cubic yards of concrete are needed?
Correct Answer
B) 28.5 CY
Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.
Why This Is the Correct Answer
Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the subcontractor quantity check at the shipping-office break area, 106 sleeves are included in the firestopping sleeve work. At 1.0 labor hours per sleeve, how many labor hours are budgeted?
Next Question
The Tampa crew finds this floor-opening condition: cover shifted after material staging. Which safety action is required before traffic continues?