During the crew-release check at the airport service-court canopy, a site crew must complete 7175 LF of concrete sidewalk placement. If planned production is 160 LF per day, how many whole work days should be scheduled?
Correct Answer
D) 45 work days
Crew days equal quantity divided by daily production, rounded up to whole days.
Why This Is the Correct Answer
Crew days equal quantity divided by daily production, rounded up to whole days.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Using the drawing index, which sheet should you open for the plumbing fixture schedule?
Next Question
At the museum back-of-house corridor, during the next-week procurement cycle, the exam-room perimeter requires 282 LF of rubber wall base plus 4% waste. Stock comes in 120 ft coils. How many coils are required?
