Project MgmtConstructionmedium63% of exam part

At the museum back-of-house corridor, during the next-week procurement cycle, the exam-room perimeter requires 282 LF of rubber wall base plus 4% waste. Stock comes in 120 ft coils. How many coils are required?

Correct Answer

B) 3 coils

Linear stock count equals required length with waste divided by stock length, rounded up.

Answer Options
A
2 coils
B
3 coils
C
4 coils
D
5 coils

Why This Is the Correct Answer

Linear stock count equals required length with waste divided by stock length, rounded up.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.