At the manufacturing clean-room chase, during the preconstruction estimate lock, the selective demolition debris produces 307 CY of debris volume, with 15% swell or handling allowance. Each container holds 30 CY. How many dumpsters are required?

Correct Answer

C) 12 dumpsters

Container count equals adjusted debris volume divided by container capacity, rounded up.

Answer Options
A
10 dumpsters
B
13 dumpsters
C
12 dumpsters
D
11 dumpsters

Why This Is the Correct Answer

Container count equals adjusted debris volume divided by container capacity, rounded up.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.