At the manufacturing clean-room chase, during the preconstruction estimate lock, the selective demolition debris produces 307 CY of debris volume, with 15% swell or handling allowance. Each container holds 30 CY. How many dumpsters are required?
Correct Answer
C) 12 dumpsters
Container count equals adjusted debris volume divided by container capacity, rounded up.
Why This Is the Correct Answer
Container count equals adjusted debris volume divided by container capacity, rounded up.
Why the Other Options Are Wrong
Option A: 10 dumpsters
10 dumpsters is below the supported result for selective demolition debris; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 13 dumpsters
13 dumpsters is above the supported result for selective demolition debris; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 11 dumpsters
11 dumpsters is below the supported result for selective demolition debris; it likely omits allowance, conversion, coverage, or final round-up.
Memory Technique
Measure to container, adjust for count, then let Superintendent Checks set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Demolition methods; dumpster capacity planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
While preparing the look-ahead planning meeting for the storm-shelter entry vestibule, the wall backup area for air-barrier sheet covers 4300 SF, with 8% added for laps and cuts. Each roll covers 500 SF. How many rolls are needed?
Next Question
From panel schedule S1, what breaker is listed for S1-4?