At the college lab corridor, during the crew-release check, a equipment-support slab is 48 ft by 8 ft by 10 in. Including 3% waste, how many cubic yards of concrete are needed?

Correct Answer

C) 12.2 CY

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Answer Options
A
11.9 CY
B
142.2 CY
C
12.2 CY
D
13.7 CY

Why This Is the Correct Answer

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.