EstatePass
Project MgmtConstructionmedium63% of exam part

For the preconstruction estimate lock at the university bookstore shell, a drywall crew must complete 17050 SF of abuse-resistant board area. If planned production is 1230 SF per day, how many whole work days should be scheduled?

Correct Answer

B) 14 work days

Crew days equal quantity divided by daily production, rounded up to whole days.

Answer Options
A
12 work days
B
14 work days
C
16 work days
D
15 work days

Why This Is the Correct Answer

Crew days equal quantity divided by daily production, rounded up to whole days.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.