For the field-takeoff reconciliation at the restaurant grease-interceptor area, the overhead pipe rack is 198 ft long and hangers are placed at 8 ft on center, including one at the starting end. How many hangers are needed?
Correct Answer
D) 25 hangers
Count the spaces along the run, then include the starting item.
Why This Is the Correct Answer
Count the spaces along the run, then include the starting item.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Palm Bay crew will work at an unprotected roof edge 7 ft above the lower level. Which control should be in place before work begins?
Next Question
The field condition is: the project condition shows that interior board is moisture sensitive. Which release decision best matches the condition?