The foreman is preparing the next work area, and the controlling field constraint is that hardware prep depends on templates. Which door hardware method should be used?
Correct Answer
D) Select verify template and handing before prep
verify template and handing before prep best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
verify template and handing before prep best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: Select field drill without template
Select field drill without template addresses a neighboring field issue, but not the condition or method control required for hardware coordination.
Option B: Field method: Select install closers before frame alignment
Field method: Select install closers before frame alignment addresses a neighboring field issue, but not the condition or method control required for hardware coordination.
Option C: Select ignore fire-rating hardware listing
Select ignore fire-rating hardware listing addresses a neighboring field issue, but not the condition or method control required for hardware coordination.
Memory Technique
Hardware Coordination method for Foreman Selecting: condition first, tool second.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Openings methods; hardware preparation and coordination; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the look-ahead planning meeting at the storm-shelter entry vestibule, the open ceiling area for dryfall ceiling paint is 3400 SF and requires 1 coat. At 325 SF per gallon, how many gallons are required?
Next Question
The Palm Bay work area has this housekeeping condition: debris blocks the emergency route. Which safety correction should be made?