In the look-ahead meeting, the constraint is that the controlling field constraint is that wood doors arrive before conditioning. Which storage method should the project team carry?
Correct Answer
C) Select dry off-floor protected storage
dry off-floor protected storage best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
dry off-floor protected storage best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: Select flat stacking on damp slab
Select flat stacking on damp slab belongs to a different file or record trail; it does not prove the finish material storage event.
Option B: Select weather-exposed staging
Select weather-exposed staging belongs to a different file or record trail; it does not prove the finish material storage event.
Option D: Material choice: Select early removal of protection
Material choice: Select early removal of protection belongs to a different file or record trail; it does not prove the finish material storage event.
Memory Technique
Finish Material Storage proof for Manager Checking: event, approval, receipt, follow-up.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Material handling methods; storage protection for finish materials; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass