The foreman is preparing the next work area, and the controlling field constraint is that heat and wind may cause rapid slump loss and surface drying. Which placement control should be used?

Correct Answer

B) Select cooling shade timely discharge and curing

cooling shade timely discharge and curing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
Select set-retarding admixture as approved
B
Select cooling shade timely discharge and curing
C
Select evaporation reducer during finishing
D
Select windbreaks and sunshades at the placement

Why This Is the Correct Answer

cooling shade timely discharge and curing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.