A subcontractor asks for direction after noting that the project condition shows that water must move to the drain. Which base material best fits the work?

Correct Answer

C) Use clean open-graded drainage stone

clean open-graded drainage stone best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
Use clayey fill at drain line
B
Use fine sand without filter control
C
Use clean open-graded drainage stone
D
Use oversized rubble with voids

Why This Is the Correct Answer

clean open-graded drainage stone best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.