For the upcoming operation, the key field fact is that the project condition shows that water must be directed to drain. Which roof slope material should govern the choice?
Correct Answer
B) Use tapered insulation cricket to drain
tapered insulation cricket to drain best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
tapered insulation cricket to drain best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: Use same-thickness boards over low spot
Use same-thickness boards over low spot may relate to another site control, but it does not remove or guard the tapered insulation layout exposure being tested.
Option C: Use field-cut random wedges
Use field-cut random wedges may relate to another site control, but it does not remove or guard the tapered insulation layout exposure being tested.
Option D: Use cover board used as slope layer
Use cover board used as slope layer may relate to another site control, but it does not remove or guard the tapered insulation layout exposure being tested.
Memory Technique
the controlling choice lock for Manager Checking: condition is the harm, roofing is the guard.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Roofing methods; tapered insulation and cricket layout; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The foreman is preparing the next work area, and the controlling field constraint is that sediment must be kept out of inlet. Which site-control material should be used?
Next Question
During the pre-installation review, the field issue is that the work should be released only if the team addresses that deep formed concrete must be consolidated inside the form. Which concrete tool is the best match?
