The construction team is coordinating a method decision because groundwater must be lowered before footing work starts. Which water-control method is best?

Correct Answer

B) wellpoints or sump pumping as designed

wellpoints or sump pumping as designed best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
eductor system for low-permeability soil
B
wellpoints or sump pumping as designed
C
cutoff trench or cutoff wall
D
gravel working mat after water control

Why This Is the Correct Answer

wellpoints or sump pumping as designed best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.