From the delivery apron plan, what paved area should be used?
Correct Answer
A) 1,440 sf
72 x 20 = 1,440 sf.
Why This Is the Correct Answer
72 x 20 = 1,440 sf.
Why the Other Options Are Wrong
Option B: 1,320 sf
1,320 sf is below the supported result for site dimension takeoff; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 1,560 sf
1,560 sf is above the supported result for site dimension takeoff; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 1,680 sf
1,680 sf is above the supported result for site dimension takeoff; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Delivery Apron takeoff: count the condition before counting the package.
Reference Hint
Open-book path: turn to sheet C-221 in the plan packet, then use the SITE DIMENSION PLAN - DELIVERY APRON note/table before checking P&P Commercial Construction plan-reading guidance.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The Bonita Springs site has this projection hazard: anchor rods are uncapped in the walkway. Which safety control is needed?
Next Question
While preparing the subcontractor quantity check for the marina restroom shell, the change-order payment shows a $87,250 approved change order. If 5% is withheld, what retainage holdback should be shown?