How far in advance must a local code exemption be certified to the local board under s. 553.80(3)(b)3?
Correct Answer
A) 10 days prior to implementation
Section 553.80(3)(b)3: "Each code exemption, as defined in sub-subparagraphs 1.a., b., and c., shall be certified to the local board 10 days prior to implementation and shall only be effective in the territorial jurisdiction of the enforcement district or local enforcement agency implementing it." The exemption is local in effect as well as in origin.
Why This Is the Correct Answer
Section 553.80(3)(b)3: "Each code exemption, as defined in sub-subparagraphs 1.a., b., and c., shall be certified to the local board 10 days prior to implementation and shall only be effective in the territorial jurisdiction of the enforcement district or local enforcement agency implementing it." The exemption is local in effect as well as in origin.
Why the Other Options Are Wrong
Option B: 60 days prior to implementation
The period is 10 days, not 60.
Option C: 30 days prior to implementation
The period is 10 days, not 30.
Option D: At the next regular meeting after implementation
It is certified before implementation, not after.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
The bidding instructions require discrepancies to be submitted through a designated written prebid clarification process. A civil plan conflicts with the utility specification. What should the bidder do?
Next Question
A crew performing roofing work will install edge metal on a low-slope roof with an unprotected edge 12 feet above the lower level. What should the GC coordinate before the crew is exposed?
