What limits apply to an annual facility maintenance permit used by a school board?
Correct Answer
C) Not more than $200,000 per project, and the permit is valid for 1 year
Section 553.80(6)(d) allows these permits for routine maintenance, emergency repairs, refurbishment and minor renovations: "The amount expended for maintenance projects may not exceed $200,000 per project. A facility maintenance permit is valid for 1 year." A detailed log must be kept and submitted annually, and a pattern of violations lets the building official withhold future permits.
Why This Is the Correct Answer
Section 553.80(6)(d) allows these permits for routine maintenance, emergency repairs, refurbishment and minor renovations: "The amount expended for maintenance projects may not exceed $200,000 per project. A facility maintenance permit is valid for 1 year." A detailed log must be kept and submitted annually, and a pattern of violations lets the building official withhold future permits.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass