A contractor asks a subcontractor to sign away its right to prompt payment interest at the time the subcontract is executed. Is that effective?

Correct Answer

C) No, the right may not be waived before a payment is due

Section 715.12(6)(d) provides that an obligee may not waive the right to receive interest before a payment is due under a covered contract, but may waive interest on a late payment on or after the date that payment is due. The timing of the waiver, not its form, is what decides.

Answer Options
A
Yes, if the waiver is conspicuous and separately signed
B
No, the right may never be waived at any time
C
No, the right may not be waived before a payment is due
D
Yes, the parties being free to allocate the risk by contract

Why This Is the Correct Answer

Section 715.12(6)(d) provides that an obligee may not waive the right to receive interest before a payment is due under a covered contract, but may waive interest on a late payment on or after the date that payment is due. The timing of the waiver, not its form, is what decides.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.