The punch list on a city project is created on June 2. By when must the city pay the remaining contract balance less the withholding the statute allows?
Correct Answer
A) 20 business days after the list is created
Section 218.735(7)(e) runs 20 business days from creation of the list, not from completion of the listed work. Payment for the amount held back under that paragraph comes later, when the contractor submits a request after finishing the items, under s. 218.735(7)(f).
Why This Is the Correct Answer
Section 218.735(7)(e) runs 20 business days from creation of the list, not from completion of the listed work. Payment for the amount held back under that paragraph comes later, when the contractor submits a request after finishing the items, under s. 218.735(7)(f).
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A supplier with no contract with the general contractor begins delivering materials to a bonded public job on May 1. By when must it tell the contractor it will look to the bond?
Next Question
After a permit is issued, when may the local enforcing agency require substantive changes to the plans?
